2751 E Oakland Park Blvd
Live Tracker
v9.1
Critical Path Position
0% 0/22 steps
▶ DO NEXT · WEEKEND → MONDAY 6/15
This weekend: Freddie electrical markups to Jim · send AC unit + water-heater model numbers to Jim. Monday 6/15: Jim Diehl review meeting — run the 7-question checklist below, lock the mop-sink FDACS posture.
Master reference: Building Facts Brief v5.2 · stamped drawings target 100% week of 6/15 · final Jim payment on completion
▸ Monday 6/15 — Jim Meeting Checklist (7)
  1. Caster bar — classification: movable equipment / N.I.C. acceptable? Rolling-table MVP (solid top on locking casters) sufficient? What construction parameters hold the classification?
  2. Caster bar — pass-through: open walkway kitchen → behind bar → customer floor, no barrier/doorway — acceptable? If a barrier is required, minimum construction?
  3. Caster bar — ADA §904.4: can the lowered accessible counter segment sit near the pass-through end of the bar?
  4. Mop sink / FDACS posture: toilet removal vs. splash partition — which is the more defensible engineering posture, and what partition spec satisfies a typical inspector?
  5. Pergola (future phase): movable-equipment path vs. permitted-structure path in Broward HVHZ — Section D's six questions.
  6. Occupant load: confirm ~38 / Group B §303.1.1 and single-restroom count.
  7. Life safety: confirm no sprinkler / no fire alarm / single exit.
Active Concerns 6 open
Upcoming Dates
▸ Recently Resolved / Wins (8) — click to expand
Next Blocker
Critical Issues 0 open
Next Three Actions
1
Mon 6/15 — Jim review meeting. Run the 7-question checklist. Lock mop-sink posture (C.4) — it has FDACS inspection consequences.
2
This weekend. Freddie electrical markups to Jim. Send AC unit + water-heater model numbers to Jim.
3
This week, in parallel. File DR-1 sales-tax registration (free, ~20 min). Start Certificate of Use application at FTL DSD. Confirm with FTL Business Tax Office whether BTR can run pre-CO (954-828-8000).
4
On drawings complete (~6/19). Assemble permit package. Decide GC-of-record vs owner-builder (affects whose COI goes in the package). SUBMIT.
5
Same week. Shop IDB + subs for hard line-item numbers against the stamped set. Financial deep-dive session AFTER quotes land — not before, otherwise it's analysis on guesses.
Critical Path
Stamped drawings → permit → CO → licenses → FDACS → legal Grand Opening · 22 gates · Tracks A/B/C/D · Gate Map 6/12
REGULATORY GATE MAP · 6/12 — Master sources: Building Facts Brief v5.2 + Master Regulatory Gate Map (June 12, 2026). Business model at GO: kava/specialty beverage bar + prepackaged retail (incl. kratom). No cooking, no food prep. Air fryer = later phase, deferred.
Gate-Critical Checkpoints Permit → CO → FDACS
Items that gate the permit, the CO, or opening day
Customer restroom — Maximum Extent Feasible — CMU-bound room ~52.75″ × 59.5″ cannot meet 60″ ADA turning space. Proceeds as MEF per ADA §202.3 / FBC-EB §306.6. Sealed technical-infeasibility memo accompanies the permit set (Access Board Guide Ch. 2, Feb 2014 + DOJ Title II preamble). Verified at standalone BADAACCESS inspection.
Source: Jim Brief C.3 · 2010 ADA Standards · FBC-Accessibility 2023 · ICC A117.1-2017
Occupant load — hold Group B under 50 — calculated ~38 at 15 SF/person (IBC §303.1.1). Crossing to 50+ flips occupancy to Group A-2: heavier fixture ratios + 3:2 women's water-closet requirement. Tune seating to maintain. Jim confirms calc Monday.
Source: Jim Brief E.1 · IBC §303.1.1
Mop / service sink — required — FBC-P Table 403.1 Note h waives it only at ≤15 occupants; ~38 exceeds the ceiling. Shown on drawings as pre-existing at the employee-restroom fixture connection (sink previously swapped) — no new rough-in. FDACS cross-contamination posture (toilet removal vs. splash partition) locks Monday (C.4).
Source: Jim Brief C.4 · FBC-Plumbing Table 403.1 Note h
FDACS — three sinks required — dedicated handwash + 3-compartment + mop/utility. Handwash and 3-comp land in the kitchen feeds (the headline new construction); mop sink pre-existing.
Source: Jim Brief E.3 · Rule 5K-4 FAC
FDACS initial inspection — cannot operate without it — after CO, before opening. Sinks, floors/walls/ceilings (FRP = smooth, nonabsorbent, cleanable), toilet separation, lighting, premises. File permit application ~14 days pre-open; can file during build.
Source: Rule 5K-4 FAC · Gate Map C1–C2
Kratom 7-OH compliance audit — emergency rules 2ER25-3 + 5KER26-1 in force. Every SKU <400 ppm 7-OH+isomers (dry weight) · labels list ppm dry-weight · COAs on file · 21+ sales. Required before stocking shelves. Audit any remaining 4242 inventory before transfer.
Source: 2ER25-3 (FL AG) · 5KER26-1 (FDACS, Mar 2026)
Energy Code C503 — required for the change of occupancy. Calculation owed by Jim Diehl inside the stamped set.
Source: FBC Energy Code C503 · Jim Brief E.4
Caster bar — ADA §904.4 accessible counter segment — wherever customers pay: ≥36″ long at ≤36″ high (parallel approach) or ≥30″ with knee clearance (forward approach). Built into one bar module. Bar itself shown as movable equipment / N.I.C. — classification parameters confirmed with Jim Monday (C.5).
Source: Jim Brief C.5 · ADA §904.4
Life safety — no sprinkler / no fire alarm / single exit — assessed acceptable at ~38 occ Group B (FBC 2023 + NFPA 101). Jim confirms Monday. Fire-Rescue signs off within the permit/CO process.
Source: Jim Brief E.2 · FBC 2023 · NFPA 101
Regulatory Bodies — Who Governs ANK
The complete list · 10 bodies · Gate Map Part 1
#BodyGoverns for ANKInstrument
1FTL Development Services (DSD)Building permit, plan review, inspections, CO, Certificate of Use (zoning), sign permitBuilding permit → CO · Certificate of Use
2FTL Business Tax OfficePrivilege of operating in city limits (FTL Code Ch. 15)City BTR
3FTL Fire-RescueFire/life-safety review within permit + possible operational walkthroughSign-off within permit/CO
4Broward County Tax CollectorCounty-level business tax (in addition to city)County BTR
5FDACS — Div. of Food SafetyFood establishment permit (beverage = Part 1, Rule 5K-4 FAC) · kratom retail rulesAnnual Food Permit + inspection · 7-OH compliance
6DBPR — Alcoholic Bev. & TobaccoTobacco retail (only if selling tobacco/nicotine)ABT-6028 dealer permit
7FL Dept. of RevenueSales & use tax on retail salesDR-1 registration → DR-11 certificate
8FL Dept. of State — SunbizCorporate good standingAnnual Report — FILED 6/12 ✓
9IRS / payroll bodies941s, payrollIn motion via CPA (Annmarie)
10Broward BSIP (via FTL Building)50-year recertification (building 1965 · 40-yr done 2010)Recert filing — Nick handling personally
Operating Licenses — Track B Sequence
Newly mapped 6/12 — these were NOT in the prior path
B1 · Certificate of Use — zoning verification of kava-bar use at this address. Can apply pre-CO; issuance ties to compliant premises. [EST] $50–$200.
Source: fortlauderdale.gov DSD [VERIFIED requirement 6/12]
B2 · City BTR — required by FTL Code Ch. 15 before operating. After/with Certificate of Use, before opening day. [EST] $50–$200/yr (Oct 1–Sep 30 year).
Source: fortlauderdale.gov/business [VERIFIED requirement 6/12]
B3 · Broward County BTR — required in addition to city; city BTR first. BTExpress online, 24–48 hr processing. [EST] $27–$150/yr.
Source: browardtax.org [VERIFIED requirement + sequence 6/12]
B4 · DR-1 sales-tax registration — THIS WEEK. Free online at floridarevenue.com, ~20 min. Before first taxable sale. Yields DR-11 Certificate of Registration.
Source: floridarevenue.com [VERIFIED — standard statewide]
B5 · Sunbiz Annual Report 2026 — ✓ DONE — filed, confirmed 6/12/2026. Corporate good standing intact.
Source: sunbiz.org · Nick 6/12
Regulatory Fee Stack
Fees only — NOT construction · Gate Map Part 3
ItemCost
FTL building permit fee[EST] ~2–3.5% of declared construction value — verify on FTL fee schedule at submission
Certificate of Use + City BTR + County BTR[EST] $130–$550 combined
FDACS food permit (Part 1)[EST] $130–$650/yr — verify exact category fee at application
ABT-6028 tobacco (only if stocking)$50
DR-1 sales-tax registration$0 online
Sunbiz Annual ReportDONE — paid
Exterior sign permit[EST] $100–$300
TOTAL REGULATORY (ex-construction, ex-permit-fee, remaining)≈ $850–$2,250
Construction cost is the real exposure — unknown until IDB/sub quotes land against the stamped set. The single most important unknown in the company right now.
Confirmed NOT Applicable
Bodies with no gate for this scope
DBPR Hotels & Restaurants — excluded: beverages/prepackaged only, §509.013(5)(b)7., F.S. [VERIFIED 6/12]. Air fryer = later phase, deferred — re-evaluate jurisdiction only if/when added.
DOH — municipal water/sewer; no well, no septic.
DEP stormwater — tenant build-out, no site disturbance.
Federal FDA — no gate; kava retail prep is state-governed.
DBPR ABT (tobacco) — conditional: drops off entirely if ANK does not stock tobacco/nicotine at GO. Decision open.
Open Verification Items [CHECK]
The honest list · Gate Map Part 5
Exact FTL permit fee % + Certificate of Use fee — at application; FTL fee schedule.
FDACS Part 1 exact annual fee for this category — at application.
Fire-Marshal operational walkthrough required for Group B <50, no suppression? — ask during permit intake.
BTR / Certificate of Use parallel with open building permit? — FTL Business Tax Office, 954-828-8000 (typical: yes, issuance conditioned).
Tobacco stocking decision — will ANK stock tobacco/nicotine at GO? If not, ABT-6028 drops off entirely.
Property Identity
Address
2751 E Oakland Park Blvd, Fort Lauderdale, FL 33306
Lease §1.1(b)
Folio
4942-24-03-0050
BCPA
Year Built
1965 · CO #5388 (10/19/1965)
Microfilm p0022/p0024 · BCPA lists 1966
Suite SF
~873
Lease
Building SF
4,849
BCPA
Construction
CBS · 8″ CMU · RC foundation · Type II
Microfilm p0024 · 1965 SFBC Group G, Fire Zone 2
Zoning
CB
BCPA
Flood Zone
AE
FEMA NFHL
Assessed Value
$851,560
BCPA 2026
Lease & Landlord
Term
5 years from Feb 1, 2026
Rent Commencement
Apr 1, 2026
CAM
18%
Landlord Entity
2747 Oakland LLC
Landlord Contact
Kenneth Fisher
Property Mgr
Patti Franco
Lockbox
Rear gate · code 2751
Insurance Bound
WC + GL + Property bound · COI to Patti Franco · D2 DONE 4/27
Insurance memo 5/18/2026
Source Documents
Project records · click to open / download
Building Use History
1965
Built — Sepper Development Co. / Sepper Construction · Architect Richard A. Baker · CO #5388 issued Oct 19, 1965 · originally filed under 2749 E Oak Pk Blvd (bay renumbered 2751) · 2751 + 2747 built as one structure, single construction event
Source: Microfilm p0020–p0025 · permits FL-65-4067 (bldg) + FL-65-4068 (roof)
1982
Chisholm Realty tenant build-out — current interior partition layout dates to this build-out, NOT original 1965 fabric
Source: Permit #82-7116 · Robert Brewster Construction · Jim Brief B
≤ 2000
Gym — confirmed by mirror walls + ballet barres still in place + permit notation
Source: PM-00090327 HVAC permit notation "(GYM)" · on-site photos
1996–~2020
Realty Executives offices — 1,000 SF, 114-Offices class
Source: FS-23093230 Fire Safety Account · Inactive after 9/2020 violation
~2020–2026
Vacant ~5+ years
Source: FS-23093230 inactive status + lease commencement Feb 2026
2026 →
Awa Na Kava kava bar (Phase 1)
Source: Executed lease 2/1/2026
Frank Adam Main Panel — Circuit Map
125A 1-phase 3-wire 120/240V · UL Listed Class N1 Issue 4808 · 16 of 20 slots used · 4 spare
SlotBreakerCircuit Description
120ABathroom Power
220ALighting
320ASingle Receptacle West Wall
420ATrack Lighting
520AReceptacles N Wall + Fans
620AReceptacles W Wall
720AReceptacle East Wall (middle)
820AEast Receptacle (south end)
9— SPARE —
10— SPARE —
1120AWest Receptacle (southernmost)
1220AOutside Lights
1315AReceptacle on NE Wall (only 15A in panel)
1420AWest Receptacle (NW)
1520Alabel faded — unverified
1620AEast Wall Receptacle (middle)
1720AReceptacle East Wall (south)
1820AEast Receptacle (north end)
19— SPARE —
20— SPARE —
Panel installed by Albert N. Siefert (EC0002423) per PM-08120788, December 2008.
Existing Mechanical / Electrical Infrastructure
Main Panel
Frank Adam 125A · 16/20 used
Photos + PM-08120788
HVAC
3-ton rooftop · 2000 install · nameplate model # to Jim this weekend
PM-00090327 · feeds mechanical sheet
Water Heater
Existing original · attic above bathrooms · no change · model # to Jim
Jim Brief B · feeds plumbing sheet
1965 Original Service
400A dual-meter EMT · since downsized
Microfilm p0024
Bathroom Exhaust
Existing ceiling fan · functional
Photos · existing
Drop Ceiling
2x4 acoustic · disturbed (per directive)
Photos · Nick directive 4/27
Mirror Walls
Both E + W · owner-side demo · no permit trigger
Photos · gym era · MIRROR risk
Customer Restroom
Retained as-is · WC + wall-mount corner sink (vanity swapped) + fan + GFI · adds: 2 ADA grab bars + FRP
Jim Brief B/C.3 · shown as existing
Employee Restroom
Existing utility/mop sink (swapped at same connection) + WC · FRP · FDACS posture pending C.4
Jim Brief B/C.4 · lock Monday
Handwash Sink
Owned · lands in kitchen feeds (stamped set)
Nick · Jim Brief C.2
3-Comp Sink
Owned · lands in kitchen feeds (stamped set)
Nick · Jim Brief C.2
Floor
Carpet REMOVED · concrete subfloor
Photos · concrete exposed
Storage Room (abandoned bath)
Plumbing access · cast iron drain + copper supply + cleanout documented
Site recon 4/27 · soil stack confirmed at 3 points
Permit History (LauderBuild)
DatePermit #TypeDescriptionStatus
2011-09-07PM-11090400Re-RoofReroof flat 3,743 SF · Manning/All American Roofing CCC045912 · $26,000Complete
2010-04-01PM-10040010Building RecertForty Year RecertificationComplete
2008-12-12PM-08120788ElectricalReplace 125A Main Disconnect · Albert Siefert EC0002423Complete
2000-09-07PM-00090327HVACReplace 3-ton unit, raise on stand (Gym) · Worrell/State Energy CAC056704Complete
2000-08-18PM-00081518Re-RoofReroof 9 SQ flat roof · Manning/All American Roofing CCC045912Complete
1996-11-25FS-23093230Fire SafetyRealty Executives · 1,000 SF · ABC 9/20 ext · NO sprinklers/smoke/standpipeInactive
1982#82-7116Interior Build-OutChisholm Realty tenant build-out · Robert Brewster Construction · current partition layoutComplete
1965-07-28#9484A/COne 3-ton rooftop electric A/C · Air Conditioning Associates (Wilton Manors)Complete
1965-06-22FL-65-4068RoofOriginal BU roof on 2.5″ Porex deck · Sepper ConstructionComplete
1965-06-22FL-65-4067BuildingOriginal construction · CBS, RC foundation, 1 story · Sepper Dev. / R.A. Baker architect · CO #5388 (10/19/1965)Complete
Original PDF ↓
Site Observations & Notes
Site recon batch · April 27, 2026 · existing-conditions facts now consolidated in the Building Facts Brief (Section B) — the master source for the stamped set
Storage Room (Abandoned Bathroom) — Plumbing Access
A second space distinct from the operational restrooms. Shelving was removed to expose existing plumbing. Cast iron drain stack visible vertical center · copper supply line with yellow-handle shutoff valve on left · cleanout access at floor. The 4″ cast-iron soil stack is confirmed at three points (Jim Brief B). Note: the FDACS mop sink is NOT here — it is pre-existing at the employee-restroom fixture connection (Jim Brief C.4); posture locks Monday.
Source: Site recon photo 4/27 · Jim Brief B/C.4
Stored Contents (unit to be clear before build work)
Materials documented inside the unit 4/27: futon, ladders, rolling tool chest, plywood signage letter, hand truck, etc. Drop ceiling intact in this view. Gym-era floor lane markings visible. Exit-marked rear door right.
Source: Site recon photo 4/27
▣ Proposed Build-Out — Design Intent
The target we're building toward. Renders from the Building Facts Brief (design intent — the as-stamped drawings govern). Click any image to enlarge.
STATUS 6/12 — IDB out of the loop by their own instruction (work direct with Jim to minimize cost). Re-engage Rick Doremus / Brian LeTulle with the completed stamped set week of 6/15 for permitting + build quote — feeds the GC-of-record vs owner-builder decision. Detail below reflects the April engagement record.
Innovative Design Build, Inc.
General Contractor
Rick Doremus (President) · 954-592-9179 Brian LeTulle (VP) · 954-444-2902 Jim Diehl, PE (Engineer, route via Rick/Brian) · 954-297-5584
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu PM/eve
Pricing
Pending
Timeline
Pending
Contract
Not signed
Deposit
Not paid
Drawings Stamped
Pending Jim Diehl

Scope Summary (from Brief v2)

  • General contractor coordination across plumbing, electrical, framing, finishes
  • Engineering drawings via Jim Diehl, PE — stamped to scope locked with Dan + Marcos
  • Permit application submission online via FTL Accela
  • Build sequencing and inspection coordination across 6 inspections + 6 gates
  • Phase 2 strategy note: Discuss feasibility of single-round permitting that includes DBPR plan review + indoor hookah service review in parallel with Phase 1, to enable single rollout vs phased rollout when Phase 1 is permit-ready

Linked Path Steps

  • Steps 9–12: Engineering drawings → permit drafting → permit submission
  • Steps 18–22: Inspection coordination (mechanical / framing / insulation / drywall screw)
  • Steps 23, 27: Finishes coordination + Final building inspection
  • Step 26: BADAACCESS inspection (separate, ADA verification)
STATUS 6/12 — Scope per the stamped set: kitchen feeds are the headline new construction. Mop sink + wall-mount corner sink are pre-existing at the same supply/drain points — no new rough-in, shown as existing (Jim Brief B/C). Shop Dan Berg line-items against the stamped set week of 6/15. Detail below reflects the April brief.
Dan Berg
Plumbing — Oakland Park Plumbing
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu AM joint w/ Marcos
Pricing
Pending
Timeline
Pending

Scope Summary (from Brief v2)

  • Hand wash sink rough-in (existing fixture)
  • 3-compartment sink rough-in (existing fixture)
  • Mop sink (FDACS Part 1 §10 required) — existing in employee bathroom
  • Existing bathrooms (turn-key)
  • Verify lavatory drain has air gap (if required) & backflow preventer is installed
STATUS 6/12Freddie Brown electrical markups (panel/circuits/loads) due this weekend → electrical sheet of the stamped set. Kitchen feeds are the new load; Frank Adam 125A has 4 spares (PANEL risk). Shop Marcos / S&R line-items against the stamped set week of 6/15. Detail below reflects the April brief.
Marcos Coelho
Electrical — S&R Electric
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu AM joint w/ Dan
Pricing
Pending
Timeline
Pending

Scope Summary (from Brief v2 + Site Recon)

  • Power requirements for build-out
Open Risks & Issues
Live tracking · resolves auto-cascade to Dashboard