Project Tracker
2751 E Oakland Park Blvd
PM
Critical Path Position
0% 0/34 steps
Next Blocker
Critical Issues 0 open
Cost Burn
$0
of $25,000 target
$25,000
remaining
0% Hard cap: $35,000
Next Three Actions
1
Send briefs to Dan, Marcos, IDB tomorrow morning (Tue 4/27 8:00–8:10 AM).
2
Phone calls 9:00–9:30 AM to confirm receipt and request earliest walkthrough availability.
3
Request Thursday AM joint meeting with Dan + Marcos before Thursday afternoon/evening meeting with IDB — so subcontractor inspection findings inform initial engineer drawings, formally request ADA Exemption, and confirm total required scope, project cost, and initial timeline ASAP.
Recent Discussion VIEW ALL →
Critical Path
Briefs in hand → legal Grand Opening · 34 steps · 6 gates · 6 inspections
Critical Checkpoints All Phases
Items that gate the permit / opening
ADA Exemption — critically urgent. Two defenses ready: disproportionate cost (20% rule) + technical infeasibility (22 SF cannot fit 60" turning radius). File with permit application.
Source: BEACON_MASTER_2751OPB · FBC 2023 · NFPA 101
BSIP 50-Year Recertification — status UNKNOWN. Building is 1966 (60 years). 40-year recert was completed 2010 (PM-10040010). 50-year would be due 2026. Catastrophic if overdue. Call FTL Building Services to verify.
Source: BCPA · LauderBuild PM-10040010 · BEACON Run 3
Kratom 7-OH compliance audit — Florida emergency rules 2ER25-3 + 5KER26-1 (March 2026, EFFECTIVE NOW). Pull COAs from HNR Distribution for ALL current kratom retail SKUs. Confirm every product <400 ppm 7-OH+isomers (dry weight). Confirm every label lists 7-OH ppm on dry weight basis. Stop-sale risk if non-compliant. Phase 1 — applies today.
Source: 2ER25-3 (FL AG emergency rule) · 5KER26-1 (FDACS emergency rule, Mar 2026)
FBC Occupancy Group B — preliminary. 38–45 occupants at 15 SF/person. Under 50 threshold = no sprinklers, no alarm, single exit acceptable.
Source: FBC 2023 §303.1 · NFPA 101 calculation
Energy Code C503 — required. Change of occupancy. Calculation owed by Jim Diehl as part of stamped drawings.
Source: FBC Energy Code C503
Demising wall fire-rating — Two doorways being closed in demising walls between Suite 2751 and adjacent tenants. FBC §708 requires fire-rated assembly between separate tenant spaces (Type IIB construction, typically 1-hour minimum). Closure assemblies must include 5/8" Type X both sides + insulation + fire-rated penetration sealing. Verified at framing inspection (FBC §110.3.4) + lath/drywall screw inspection (FBC §110.3.5).
Source: FBC §708 · §110.3.4-5 · DEMISE risk card · Site photos 4/27
Microfilm records pull (FTL Building Archives) — Required to identify CI-06 unknown pipe + close gaps in property history. Nick previously denied desk access pre-lease. New strategy: bring executed lease + tenant authorization letter from Patti Franco/Kenneth Fisher + know FL §119 Public Records Act citation + escalate to records supervisor by name (not desk clerk). Building permits ARE statutory public records under FL §119 — denial is challengeable.
Source: FL §119 Public Records Act · Nick directive 4/27 · CI-06 + MICROFILM risk cards
Scope of Work — Phase 1 Build
Per-trade scope summary. Subs assigned where formalized; informal labor scoped only.
DEMO
Abandoned bathroom partition demolition
Matt/Freddie scope · informal labor
DEMO
Mirror-wall removal (CI-05) — both E + W walls, gym-era infrastructure
Matt/Freddie scope · specialty handling required
FRAME
Frame closures for shared-wall openings + new partitions per Jim Diehl drawings
Matt/Freddie scope · informal labor
DRY
Drywall hang + tape/mud + screw inspection prep
Matt/Freddie scope · informal labor
PLUMB
Plumbing rough-in — handwash + 3-comp + mop sink (existing bathroom turn-key, no rough needed)
Dan Berg · Oakland Park Plumbing
ELEC
Electrical rough-in — kitchen circuits + lighting · CI-03 + CI-04 evaluations
Marcos Coelho · S&R Electric
FLOOR
Acid stain concrete — carpet already removed, subfloor exposed
Wes · Great Finishes (E-01)
FINISH
Paint, signage, trim
Kenny + Anthony · finishes labor
CEILING
Drop ceiling — disturbed state by design until past inspections, then close walls/ceilings
Per Nick directive · 4/27
FRAME
Demising wall doorway closures — 2 doorways · FBC §708 fire-rated assembly (1-hr typical) · Type X both sides
Matt/Freddie scope · Jim Diehl rating spec
PLUMB
Mopsink in storage room (abandoned bathroom) — re-use existing rough-in (cast iron drain + copper supply already exposed)
Dan Berg · saves $2K-$5K vs new run
RESEARCH
Microfilm records pull — FTL Building Archives · identify CI-06 pipe + verify full property history
Nick · with landlord auth letter + FL §119 backup
Permit Dependencies
Three permits, parallel tracks
FTL Building Permit — drives critical path. Submitted online via Accela. Revision rounds typical 7–14 days each.
Source: FTL DSD · LauderBuild Accela portal
FDACS Food Permit (Part 1 — beverage service) — parallel track. Submit ~14 days before opening. Settlement B58902 PAID IN FULL.
Source: Nick confirmed 4/26 · FDACS settlement records
Tobacco Retail (ABT-6028) — parallel, $50, 2–4 week processing. Does not delay anything.
Source: DBPR ABT · Session 4/26
FDACS Part 1 Standards (beverage service)
ANK = Part 1 (brewed kava + tea + coffee = beverage service), NOT Part 2 (prepackaged only)
Smooth nonabsorbent floors → acid stain concrete via Wes (Great Finishes). Coved at wall/floor junctures in mop areas (FDACS Part 1 §5).
Source: FDACS Min Construction Standards Part 1 §5 · E-01
Handwash sink — owned, needs rough-in. Hot+cold water through mixing valve (FDACS Part 1 §7-8).
Source: FDACS Part 1 §7-8
3-compartment sink — owned, needs rough-in. Indirect plumbed via air gap or air break (FDACS Part 1 §9).
Source: FDACS Part 1 §9
Mop sink — required (FDACS Part 1 §10). Hot water not required.
Source: FDACS Part 1 §10
Adequate ventilation — no cooking equipment, no specialized exhaust required. Existing 3-ton HVAC (PM-00090327) confirms baseline.
Source: FDACS Part 1 §13 · PM-00090327
Toilet room separation — existing bathroom is enclosed and self-closing. Cannot open directly into food prep (FDACS Part 1 §4). Verify door swing in proposed plan.
Source: FDACS Part 1 §4 · proposed floorplan
Design Inspiration & Reference
Visual + menu reference materials for design intent
Bathroom corner-mount sink — design intent
Bathroom design inspiration
Source: Nick · design intent reference 4/27
Awa Na Kava — Full-Spectrum Menu Reference (END-STATE, NOT Phase 1 opening menu) — 12-page menu PDF documenting the eventual full-spectrum offering across all phases. Phase 1 opening scope = beverages (kava/kratom tea/coffee/tea/smoothies/on-tap) + cans/bottles + shots + gummies + supplements + bulk retail kratom + CBD only. Air fryer (Phase 2 — triggers DBPR plan review), hookah (Phase 2/3 — tobacco licensing + ventilation), and THC/hemp on-site consumption (Phase 3/4) are deferred per regulatory roadmap.
Source: Nick uploaded 4/27 · Phase 1 strategy per COR-040
Property Identity
Address
2751 E Oakland Park Blvd, Fort Lauderdale, FL 33306
Lease §1.1(b)
Folio
4942-24-03-0050
BCPA
Year Built
1966
BCPA
Suite SF
~873
Lease
Building SF
4,849
BCPA
Construction
CMU / Reinf. Concrete
BCPA
Zoning
CB
BCPA
Flood Zone
AE
FEMA NFHL
Assessed Value
$851,560
BCPA 2026
Existing Floorplan
Existing — Full Layout
Full Layout (with measurements)PDF ↓
Existing — Overview
Overview (clean)PDF ↓
Existing — Front Doors Detail
Front Doors DetailPDF ↓
Existing — Bathroom + Office
Bathroom + Rear OfficePDF ↓
Existing — Bathroom Detail
Bathroom DetailPDF ↓
Proposed Floorplan — 2D
Proposed — Full Layout
Full Layout (with measurements)PDF ↓
Proposed — Overview
Overview (clean)PDF ↓
Proposed — Front of House
Front of House (bar + lounge + retail)PDF ↓
Proposed — Kitchen / Service
Kitchen / Service / Bathroom (BOH)PDF ↓
Proposed — Kitchen Detail
Kitchen Detail (sinks · 2D)PDF ↓
Proposed Design — 3D Walkthrough
Six 3D views of the proposed Phase 1 build · click any image to enlarge
3D — Top-Down Overview
Top-Down Overview (full layout in 3D)
3D — Storefront Looking In
Storefront Looking In (front cafe + lounge)
3D — Bar Back Wall
Bar Back Wall (espresso + merchandiser + TVs)
3D — Kitchen Top-Down
Kitchen Top-Down (3-comp + handwash + bath)
3D — Kitchen Sinks Detail
Kitchen Sinks + Prep Tables (3D detail)
3D — Lounge / Retail Top-Down
Lounge + Retail (top-down)
Existing Conditions Photo Gallery
Site reconnaissance · April 27, 2026 · click any photo to enlarge
Demolition Progress — Wall Reveals & Closures
Photos taken after latest demo work · April 27, 2026 · click any photo to enlarge
Storage Room (Abandoned Bathroom) — Mopsink Site
A second space distinct from the operational bathroom. Shelving was removed to expose existing plumbing connections. Cast iron drain stack visible vertical center · copper supply line with yellow-handle shutoff valve on left · cleanout access at floor. This is where the FDACS Part 1 §10 mop sink lands — re-using existing rough-in saves $2K–$5K vs new run.
Storage room plumbing reveal
Mopsink rough-in target · plumbing exposed
Source: Site recon photo 4/27 · Nick directive 4/27
Wall Cavity Behind EP Panel — Electrical Riser Exposed
Back side of the utility-room panel wall. Studs exposed. Larger junction/transformer-style box mid-wall (function TBD by Marcos). Multiple gang boxes. Cast iron soil stack vertical on left. Pink insulation right side. Conduit run at top into ceiling. The second panel inside the building is now visible OPEN with its handwritten circuit index card — capacity + source feed pending Marcos walkthrough.
Wall cavity behind EP panel
Behind utility-room panel · cavity opened
Second panel open with index card
Second panel · door open · index card visible
Source: Site recon photos 4/27 · CI-03 risk card
Demising Wall Doorway Closures (in progress)
Two doorways being closed off in demising walls between Suite 2751 and adjacent tenant spaces. Framed and sheathed with mixed materials (acoustic panel + travertine veneer remnant on storefront-side). Demising walls between separate tenant spaces require fire-rated assembly per FBC §708 (Type IIB construction) — typically 1-hour minimum. Closure assemblies must meet rating; Jim Diehl confirms in stamped drawings.
Demising closure storage side
Storage room side · old doorway being closed
Demising closure storefront side
Storefront side · doorway being closed
Source: Site recon photos 4/27 · DEMISE risk card · FBC §708
⚠ Unidentified Pipe — Possible Abandoned Propane (CI-06)
Pipe of unknown service located adjacent to the cast iron soil stack at floor level. Nick contacted the gas utility for this service area: no record of gas service ever existing here. Hypothesis: abandoned propane line from a prior tank service no longer documented. Microfilm records pull required from FTL Building Archives for full property history. (Nick was previously denied access by desk staff — strategy update needed before next visit; see CI-06 mitigation.)
Unidentified pipe at floor
Unknown pipe · floor closeup
Source: Site recon photo 4/27 · Gas utility null record · CI-06 risk card
Current Stored Contents (move-out required pre-build)
Materials currently inside the unit awaiting removal: futon, ladders, rolling tool chest, plywood signage letter, hand truck, etc. Drop ceiling intact in this view. Floor lane markings visible (gym era). Exit-marked rear door right.
Current stored contents
Stored contents · move-out before build phase
Source: Site recon photo 4/27
Frank Adam Main Panel — Circuit Map
125A 1-phase 3-wire 120/240V · UL Listed Class N1 Issue 4808 · 16 of 20 slots used · 4 spare
SlotBreakerCircuit Description
120ABathroom Power
220ALighting
320ASingle Receptacle West Wall
420ATrack Lighting
520AReceptacles N Wall + Fans
620AReceptacles W Wall
720AReceptacle East Wall (middle)
820AEast Receptacle (south end)
9— SPARE —
10— SPARE —
1120AWest Receptacle (southernmost)
1220AOutside Lights
1315AReceptacle on NE Wall (only 15A in panel)
1420AWest Receptacle (NW)
1520Alabel faded — unverified
1620AEast Wall Receptacle (middle)
1720AReceptacle East Wall (south)
1820AEast Receptacle (north end)
19— SPARE —
20— SPARE —
Panel installed by Albert N. Siefert (EC0002423) per PM-08120788, December 2008.
Building Use History
≤ 2000
Gym — confirmed by mirror walls + ballet barres still in place + permit notation
Source: PM-00090327 HVAC permit notation "(GYM)" · on-site photos
1996–~2020
Realty Executives offices — 1,000 SF, 114-Offices class
Source: FS-23093230 Fire Safety Account · Inactive after 9/2020 violation
~2020–2026
Vacant ~5+ years
Source: FS-23093230 inactive status + lease commencement Feb 2026
2026 →
Awa Na Kava kava bar (Phase 1)
Source: Executed lease 2/1/2026
Existing Mechanical / Electrical Infrastructure
Main Panel
Frank Adam 125A · 16/20 used
Photos + PM-08120788
Second Panel
Utility room · capacity TBD
Photos · CI-03 pending
FPL Device
Type-31 Load Mgmt
Photos
Mechanical Timer
Intermatic-style · function TBD
Photos
HVAC
3-ton · 2000 install (26 yr) ⚠
PM-00090327
Bathroom Exhaust
Existing ceiling fan · functional
Photos · existing
Drop Ceiling
2x4 acoustic · disturbed (per directive)
Photos · Nick directive 4/27
Mirror Walls
Both E + W · DEMO scope (CI-05)
Photos · gym era
Existing Bathroom
Turn-key · toilet + vanity + fan + GFI
Photos
Handwash Sink
Owned · needs rough-in
Nick
3-Comp Sink
Owned · needs rough-in
Nick
Floor
Carpet REMOVED · concrete subfloor
Photos · concrete exposed
Storage Room (abandoned bath)
Plumbing reveal · mopsink site
Site recon 4/27 · cast iron drain + copper supply
Demising Walls
2 doorways being closed · fire-rate per FBC §708
Site recon 4/27 · DEMISE risk card
Unknown Pipe (CI-06)
Possible abandoned propane · gas utility no record
Site recon 4/27 · gas utility null + microfilm pending
Permit History (LauderBuild)
DatePermit #TypeDescriptionStatus
2011-09-07PM-11090400Re-RoofReroof flat 3,743 SF · Manning/All American Roofing CCC045912 · $26,000Complete
2010-04-01PM-10040010Building RecertForty Year RecertificationComplete
2008-12-12PM-08120788ElectricalReplace 125A Main Disconnect · Albert Siefert EC0002423Complete
2000-09-07PM-00090327HVACReplace 3-ton unit, raise on stand (Gym) · Worrell/State Energy CAC056704Complete
2000-08-18PM-00081518Re-RoofReroof 9 SQ flat roof · Manning/All American Roofing CCC045912Complete
1996-11-25FS-23093230Fire SafetyRealty Executives · 1,000 SF · ABC 9/20 ext · NO sprinklers/smoke/standpipeInactive
Original PDF ↓
Lease & Landlord
Term
5 years from Feb 1, 2026
Rent Commencement
Apr 1, 2026
CAM
18%
Landlord Entity
2747 Oakland LLC
Landlord Contact
Kenneth Fisher
Property Mgr
Patti Franco
Lockbox
Rear gate · code 2751
Innovative Design Build, Inc.
General Contractor
Rick Doremus (President) · 954-592-9179 Brian LeTulle (VP) · 954-444-2902 Jim Diehl, PE (Engineer, route via Rick/Brian) · 954-297-5584
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu PM/eve
Pricing
Pending
Timeline
Pending
Contract
Not signed
Deposit
Not paid
Drawings Stamped
Pending Jim Diehl

Scope Summary (from Brief v2)

  • General contractor coordination across plumbing, electrical, framing, finishes
  • Engineering drawings via Jim Diehl, PE — stamped to scope locked with Dan + Marcos
  • Permit application submission online via FTL Accela
  • Build sequencing and inspection coordination across 6 inspections + 6 gates
  • Phase 2 strategy note: Discuss feasibility of single-round permitting that includes DBPR plan review + indoor hookah service review in parallel with Phase 1, to enable single rollout vs phased rollout when Phase 1 is permit-ready

Linked Path Steps

  • Steps 9–12: Engineering drawings → permit drafting → permit submission
  • Steps 18–22: Inspection coordination (mechanical / framing / insulation / drywall screw)
  • Steps 23, 27: Finishes coordination + Final building inspection
  • Step 26: BADAACCESS inspection (separate, ADA verification)
Dan Berg
Plumbing — Oakland Park Plumbing
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu AM joint w/ Marcos
CI-01 Test
Soil stack water test
Pricing
Pending
Timeline
Pending

Scope Summary (from Brief v2)

  • CI-01: Soil stack water test (verify drainage with garden hose adapter) — stack now visible at 3 points (mid-wall, bathroom branch, floor cleanout) · cast iron in serviceable visual condition
  • Hand wash sink rough-in (existing fixture, owned by Nick)
  • 3-compartment sink rough-in (existing fixture, owned by Nick)
  • Mop sink (FDACS Part 1 §10 required) — land in storage room (abandoned bathroom): cast iron drain stack + copper supply with shutoff valve + cleanout already exposed · save $2K-$5K vs new run
  • Existing bathroom (turn-key, distinct from storage room) — verify lavatory drain has air gap, backflow preventer adequate
  • CI-06 unidentified pipe at floor next to cast iron stack — pressure test for live gas (soap test or sniffer) before any wall close-up · gas utility has no record of service ever existing here
Marcos Coelho
Electrical — S&R Electric
Brief Sent
Pending — 4/27 AM
Phone Confirmed
Pending
Walkthrough
Target: Thu AM joint w/ Dan
CI-03 Assessment
2nd panel utility room: capacity, source, function
CI-04 Capacity
125A capacity (4 spare slots — tight)
Pricing
Pending
Timeline
Pending

Scope Summary (from Brief v2 + Site Recon)

  • CI-03: Second panel in utility room — verify (a) source feed, (b) amperage capacity, (c) function, (d) active vs. abandoned
  • CI-04: Main panel 4 spare slots tight — kitchen build needs ~5 dedicated. Choose: consolidate, sub-panel, or service upgrade
  • FPL Type-31 Load Management Device — confirm doesn't constrain HVAC operation
  • Mechanical timer — identify what it controls (outdoor signage / lighting / HVAC), keep or remove
  • Existing Frank Adam panel (PM-08120788, Albert Siefert EC0002423, Dec 2008) — most recent licensed electrician of record on main service
  • Power requirements for build-out (Phase 1 menu: beverages + retail)
  • Lighting plan — keep existing track lighting (circuit 4) or replace? Exterior signage circuit (12)?
Open Risks & Issues
Live tracking · resolves auto-cascade to Dashboard
Discussion Board. Use this space for project questions, research findings, status updates, and team coordination. All posts are tagged with your name and timestamp. Newest posts appear at the top.
Posting as